Mumbai : The Transportation
Infrastructure business vertical of L&T has won significant order for
Mumbai metro railway project.
The scope encompasses design, manufacture, supply, installation, integration, testing and commissioning of power supply and traction systems for 24.72 route km and provision of SCADA system for complete Metro line 4 & 4A for 32 stations, depots and receiving substation. All work will be carried out by L&T’s in-house design and execution team. The scope also includes electrical and mechanical works, Lift & Escalators for 22 elevated stations and 2 Depots, along with five years of comprehensive maintenance.
This is the third
successive order that L&T has won in the Line-4&4A corridor of Mumbai
Metro. It had earlier won the order for Package CA-234, involving rolling
stock, Communications-Based Train Control (CBTC) signalling,
telecommunications, platform screen doors and depot machinery & plant for
the entire corridor, and another order for Package CA-168, involving 19.5 km
ballast-less track-works across 15 stations.
Background:
Larsen &
Toubro is a USD 30 billion Indian multinational engaged in EPC Projects,
Hi-Tech Manufacturing, and Services, operating across multiple geographies. A
strong, customer–focussed approach and the constant quest for top-class quality
have enabled L&T to attain and sustain leadership in its major lines of
business for eight decades.
* Project
Classification
|
Classification |
Significant |
Large |
Major |
Mega |
Ultra-Mega |
|
Value in
₹ Cr |
1,000 to 2,500 |
2,500 to 5,000 |
5,000 to 10,000 |
10,000 to 15,000 |
> 15,000 |